Construction WA

Sino Iron Project

LOCATION: Cape Preston
PROJECT VALUE: $6+ Billion

The project covered a large number of sub-projects across all areas of the under-construction processing plant.  Scope of works included the supply of all supervision, labour, materials, plant and equipment, for detailed earthworks, the installation of footings, ground slabs, substations, suspended slabs, structural steel. Works consisted of the following:

  • Earthworks excavation, delivery, preparation of backfill materials, screening, backfill and compaction
  • The procurement, delivery and installation of reinforcement, cast-in items, bolt and cast-in conduit
  • Preparation, fabrication, and installation of required formwork
  • Pouring of concrete
  • Installation of security fencing, handrails, grating & support steel
  • Installation of structural steel
Sino